Eight of 15 Ukrainian Reactors Stay in Operation After Three Weeks of Conflict


Ukraine’s nuclear regulator knowledgeable the Worldwide Atomic Power Company (IAEA) on March 16 that eight of the nation’s 15 nuclear reactors had been in operation regardless of the continuing Russian invasion. Of the 4 websites with operational items, two of six at Zaporizhzhya, three of 4 at Rivne, certainly one of two at Khmelnytskyy, and two of three at South Ukraine had been in operation.

On the Zaporizhzhya web site, which Russian forces took management of on March 4, Ukrainian employees have continued to function Units 2 and 4. The items are working at “barely decreased” energy provides to the grid as a result of some energy traces had been broken by the preventing. The plant, which is the most important nuclear energy plant (NPP) in Europe, has 4 high-voltage (750-kV) offsite energy traces. Two of the 4 had been broken earlier and a 3rd line was misplaced on Wednesday. The station additionally has a standby line, which, with the one remaining energy line, “had been enough to make sure that all security techniques remained totally purposeful with out limitations,” the IAEA stated. Like different NPPs in Ukraine and elsewhere, the plant additionally has backup diesel mills that may provide web site energy if wanted.

Russian forces are additionally in command of the Chernobyl NPP—web site of the notorious nuclear catastrophe in 1986. Chernobyl, which is positioned in northern Ukraine close to the nation’s border with Belarus, was taken over on Feb. 24 very quickly after the invasion started. The IAEA stated Ukrainian employees have continued to handle day-to-day operations on the web site, the place numerous radioactive waste administration services are positioned.

The location reportedly has 211 technical personnel and guards that haven’t been capable of rotate for the reason that day earlier than the Russian forces entered the realm—in impact residing there for the previous three weeks. The Ukrainian regulator stated there was “no data whether or not and when a shift change can be potential.”

“I stay gravely involved concerning the extraordinarily troublesome circumstances for the Ukrainian employees there,” IAEA Director Common Rafael Mariano Grossi stated in an announcement on March 16.

Chernobyl misplaced all off-site energy on March 9 and was pressured to resort to diesel mills for backup energy at the moment. Ukrainian groups labored to revive the system and succeeded in repairing one of many two broken traces on March 14 at 4:45 p.m. CET. The regulator reported the road has been offering all of the required energy for the NPP, and the diesel mills have been switched off. The road can be supplying electrical energy to the close by metropolis of Slavutich. It’s unclear if the second high-voltage energy line might be repaired beneath the present circumstances.

As well as, the regulator stated on March 15 that data it obtained concerning Chernobyl was “managed by the Russian army forces,” and due to this fact, it couldn’t “all the time present detailed solutions to all” of the IAEA’s questions. This was reportedly additionally the case on the Zaporizhzhya NPP.

Regarding safeguards, the IAEA stated it was not receiving distant information transmission from its monitoring techniques put in on the Chernobyl NPP, however such information was being transferred to IAEA headquarters from the opposite NPPs in Ukraine.